Raising the Roof!

Posted on: September 29th, 2011 by Silver Lake Mennonite Camp

The rooms are partitioned, the roof is just about ready for shingles and the contractor says we are on schedule! Here are some pictures from this week.

Walls are up!

Posted on: September 22nd, 2011 by Silver Lake Mennonite Camp

Things are really moving along well. The basement floor is now poured and they have completed framing the outside walls and are now working on the inside walls. Roof trusses come Monday so the roof will go on next week and John Dyck (our Ace electrician) is driving up to re connect the electrical – thanks John!

Dining Hall Addition Underway

Posted on: September 16th, 2011 by Silver Lake Mennonite Camp

The foundation is now poured and framing begins next week! Lots of excited projects going on this fall so be sure to mark October 28, 29 & 30 into your calendars for Fall Work Weekend.